Maharajganj Installs 4,037 Solar Plants Under PM Surya Ghar Scheme

Maharajganj has installed 4,037 solar plants under PM Surya Ghar, crossing its annual target, while loan, inspection and portal cases remain pending.

S

SolarSathi

3 min read
Maharajganj Installs 4,037 Solar Plants Under PM Surya Ghar Scheme

Maharajganj: The PM Surya Ghar Muft Bijli Yojana has crossed its annual installation target in Maharajganj district. A total of 4,037 rooftop solar plants have been installed so far, against the yearly target of 3,604 installations for the financial year 2026-27.

The progress was reviewed at a meeting held at the collectorate auditorium. District Magistrate Gaurav Singh Sogarwal chaired the meeting. Officials from the electricity department, banks and solar vendor agencies attended the review.

District crosses its yearly solar target

The district had a target of 3,604 solar installations for the year. It has already completed 4,037 installations. This means the district has achieved more than its planned yearly figure.

Between April and August, the monthly target was 1,500 installations. Against this figure, officials completed 1,832 installations. The month-wise figures show steady growth:

  • April: 298 installations
  • May: 318 installations
  • June: 358 installations
  • July: 420 installations
  • August: 438 installations
  • Up to September 15: 250 installations

By September, the cumulative target stood at 3,755 installations. The district had completed 4,037 by that point. The figures show strong demand for rooftop solar systems among households in the district.

What the review meeting focused on

The meeting covered several parts of the scheme. These included solar installation work, bank loans, net metering, vendor concerns and inspections by the electricity department.

The District Magistrate asked all departments to work together so that applicants do not face delays. He said that people should not face avoidable problems during loan approval, net metering or the inspection of their solar systems.

For a rooftop solar system to work under the scheme, several steps may need to be completed. The applicant must select an approved vendor, arrange finance if required, get the system installed and complete the required inspection. Net metering also helps connect the rooftop system with the electricity network. Delays at any one stage can hold up the full process.

758 bank loan cases are still pending

The review found that 758 bank loan cases were pending for disbursement. The District Magistrate directed bank officials to complete the required formalities and release the loans without delay.

Officials were also asked to ensure that applicants complete payments such as margin money where needed. Faster action on these cases can help more households complete their solar installations.

89 solar plants await inspection

The electricity department has not yet inspected 89 installed solar plants. The pending cases are spread across four areas:

  • Maharajganj division: 41 cases
  • Nautanwa: 24 cases
  • Nichlaul: 21 cases
  • Anandnagar: 3 cases

The department has been told to clear these cases at the earliest. Inspection is an important step because it helps officials check the installation and complete the next stage of the process.

Vendor data must be updated on the portal

Details of 336 installations completed by vendors were still waiting to be uploaded to the official portal. The administration asked vendors to update the records as a priority.

Accurate portal data helps track applications, installations, inspections and other pending work. It also gives officials a clearer view of where delays are taking place. The administration directed officials to address vendor problems and keep the work moving.

Why the scheme matters for households

The PM Surya Ghar Muft Bijli Yojana aims to support rooftop solar systems for homes. Solar panels can help households produce power on their own rooftops and reduce their dependence on grid electricity. The scheme also involves financial support and a process for connecting systems to the local power network.

For residents in Maharajganj, the latest review gives a clear picture of both progress and pending work. The district has crossed its installation target, but hundreds of loan cases, inspections and portal updates still need action. Banks, electricity officials and vendors will need to keep pace with the growing number of applications.

Residents seeking information about an application should check the official scheme portal and contact the concerned electricity office or bank. They should also keep records of their application, payment, installation and inspection details.

Maharajganj NewsPM Surya Ghar YojanaRooftop SolarSolar EnergyUttar Pradesh NewsGovernment Schemes

Considering going solar?

Compare brands, products, and installers to find the best solar solution for your needs.

Get Free Quote